This project took place at a thermal power plant of 1200MW power production capacity.
Lignite produces huge amounts of ash during burning process, which has to be removed away at a sufficient distance.
The transfer of ash for this process is performed through pneumatic transport with the use of powerful industrial blowers.
In this specific case Michos SA installed and commissioned a lobe blower with capacity 7000m3/h and installed power 90kW.
At the same thermal power plant our company has delivered a big number of low-pressure industrial blowers, such as the one shown in the picture, to facilitate similar applications in the plant.